Darwin’s crew installed internal drainage system at rear total of 17 lineal feet and repaired section of front total of 16 lineal feet.. Weeping tile was installed with air gap drainage membrane and connected to existing sump pump. Drywall, studs and insulation were removed and disposed of. Installed 18’’ by 18’’ dry well at rear for system to drain.
Removed existing discharge pipe and replaced with new 4inch hard pipe 10 ft long with slope to spill unto front lawn. Draw cap was added at the end of the pipe.
Sales Consultant: Rick Deagazio
Crew: Darwin’s Crew
Jobsite Location
Internal Water Management System-Twenty Fourth St, Toronto