The Crew installed an internal drainage system in the washroom at at the back right of the house for a total of 14ft into new sump pump system in the adjacent room. A 7ft grey air gap drainage membrane was installed brought all the way up to the joist. Weeping tiles were installed and connected to the new sump pump.

The crew installed a new 1/3 HP Liberty sump pump system in the bedroom next to the bulk head wall. They drilled a discharge hole approximately 32inches off the grade and 8 inches out towards the driveway, discharge pipes were installed to run under the floor and up the wall behind the drywall cavity. Approximately 10 sq ft of drywall was removed and disposed of.

Sales Consultant: Den Ikonomi

 


Jobsite Location

Internal Water Management System on Linsmore Cr, Toronto