Joey’s crew waterproofed 21ft along the left side of the back wall to the garage. Excavation was done to weeping tile, and a 4″ weeping tile with filter and 3/4 clear gravel added above.
Hydro-guard commercial rubber was applied once the foundation wall had been cleaned and parged with hydraulic cement. After the first layer of rubberized material has been applied, a waterproofing reinforcement sheet is applied to strengthen the first layer and then lastly followed by the second layer of Hydro Guard.
One new window well was installed with a vertical drain and weepers were connected to the existing discharge.
If you are interested in these waterproofing services and would like to learn more, head over to our exterior waterproofing page.
Sales Consultant: Joe Romanelli
Crew: Joey’s Crew
Jobsite Location
External Restoration and Waterproofing w/ Window Well- Rexton Rd, Etobicoke