External Restoration and Waterproofing- Ravenbourne Cr, Etobicoke

The crew restored and waterproofed 17ft of the right wall, starting 7ft from the front going towards the fence. 75 sq ft of interlock was removed and put to the side. Excavation was done to weeping tile, and a 4″ weeping tile with filter and 3/4 clear gravel added above.
After the first layer of rubberized material has been applied, a waterproofing reinforcement sheet is applied to strengthen the first layer and then lastly followed by the second layer of Hydro Guard. 1 steel window well was installed with a vertical drain.
If you are interested in these waterproofing services and would like to learn more, head over to our exterior waterproofing page.

Sales Consultant: Ramy Morcos

Crew: Ramy’s Crew


Jobsite Location