Omar’s crew repaired the foundation wall on the right side for 42 lineal ft starting at the rear corner. Excavation was done to weeping tile, and a 4″ weeping tile with filter and 3/4 clear gravel added above. Hydro-guard commercial rubber was applied once the foundation wall had been cleaned and parged with hydraulic cement. After the first layer of rubberized material has been applied, a waterproofing reinforcement sheet is applied to strengthen the first layer and then lastly followed by the second layer of Hydro Guard.
Two (2) new window wells (42’’wide 12’’deep 12’’projection) were added to replace the existing window wells and vertical drains were also installed.
If you are interested in these waterproofing services and would like to learn more, head over to our exterior waterproofing page.
Sales Consultant: Rick Deagazio
Crew: Omar’s Crew
Jobsite Location
External Restoration and Waterproofing- Marley Cr, Burlington